1/ Definition

This Metric shows 2 figures calculated in the same snapshot, 1 for the past week, and 1 for the current week

  • For the Last week: the % respect of the Maintenance Plans managed in SAP
  • For the Current week: the number of Maintenance Plans that should be realized during the current week


2/ Objective / Target

To be defined by site

3/ Formula

  • Last week Figures: % Respect of Maintenance Plans

Number of completed Work Orders* issued from a Maintenance Plan the last week / Total Number of planned Works* issued from a Maintenance Plan for the last week

  • a completed Work order is a Work Order with 1 of its potential Closing status GS45, GS50, GS55, 6CMP, CNF, TECO feeded with a date. The rule takes the earliest date to compare with the Required end date of the notification or with the Planned Date if there is no Notification, and finally determines if OK or KO for the % Respect.
  • a planned Work is a Call, a Notification, or a Work Order coming from a Maintenance Plan. The Planned Date is generated by the Maintenance Plan depending its own parametrization (SAP Transaction IP24)
  • Current Week Figures: Number of Maintenance Plans

Number of Call, Notifications or Work Orders issued from a Maintenance Plan with Planned Date between Monday and Sunday.

4/ Frequency

Weekly

5/ SAP extraction and Detailed calculation

For every Work issued from a Maintenance Plan completed the last week, the system compares the earliest date found on a Closing status* on the Work Order (GS45 or GS50 or GS55 or 6CMP or CNF or Reference date of the TECO), against the Required End date of the Notification OR  against the Planned Date of the Call if there is no Notification.

*NB: This rule is the same used in the 2.12 Respect of Notification date, for Work order NOT issued from a Maintenance Plan

Field nameFromToI/E
WO "Closing" Status: GS45 or GS50 or GS55 or 6CMP or CNF or Reference date of the TECO of the WOMonday (W-1)Sunday(W-1)I
Only Work Orders from Maintenance Plan  I



 

5/ Example on 2 different snapshots: Week 35 and Week 36

1/ When Data are available in the Dashboard the Monday 29th of August, at the beginning of the Week 35

  • firstly, the Graph shows for the past Week 34 that 27% (15 / 55) of Works issued from a Maintenance Plan have been realized (from 22th to 28th of August)
  • secondly, the Graph shows for the current Week 35 that 49 Works should be realized (from 29th August to 4th of September), among which 4% are already done (Works anticipated)

2/ When Data are available in the Dashboard the Monday 5th of September, at the beginning of the Week 36

  • The graph shows that 71% (37/52) of the Works that were planned Week 35 are realized.

 

3/ in the BW Analytical Reporting, the report can display from aggregated level to detailed level, by Work orders.

 

 

For example, you can extract the list of Maintenance plans that were not completed during the selected week

 

 

 