| Status | Approved |
| Owner | Antonio Zappone |
| Stakeholders |
Issue
Decision is required as the when to deploy the new S4\HANA In-House-Bank.
Recommendation: Option A: Defer the deployment of IHB for all GBUs\Entities until after the second group go-live.
This is the lowest risk option in an area that is general ly cosnidered higher risk. Payments and receipts is a critical processes. There are additional layer's of complexity with running an in-house-bank along with the higher compexity custom solutions to support the internal factoring process.
Interim interfaces are required, which add compleity, however these interim interfaces are requird in most of the deployment options. The interim interfaces will be developed based on the existing interfaces from PF1\WP1 to PI1, hence they are not new design, although the will have to be adapted for the S4HANA.
Deferring the the deployment requires project resources for a longer period of time, which equates to additional cost. Required resources will be limited to IHB consultants and technical developers. Whether this is an "additional cost, or whether resources can commence later and finish later needs to be determine in the overall project planning.
Background & Context
In-House Bank
The existing IHB within ECC resides in PI1, within the legal entities SSA and SFA. SSA and SFA entities also reside in PF1 for all non IHB processes. Interfaces are current in place to link PF1 and WP1 to the IHB in PI1.
All entities are mandated to participate in the IHB process, except where it's not legally possible. For example, China, x ,x ,x , is not part of the IHB due to legal restrictions.
Internal Factoring
A high level of complexity exists with IHB largely due to the internal factoring process. Internal factoring brings benefits in the way of;
- Tax cash advantage of ~3 m€ per year for Syensqo
- Native centralisation of the cash flows onto Syensqo SA and SFA without the need to pool further
- Centralisation of the FX exposures that enable centralised and efficient hedging over the largest exposures possible
- Centralisation of the collection and credit risk allowing to streamline the CCT activities (Note: should be shared with CCT)
- Centralisation of the vendor payments allowing the streamline the A/P and Payroll activities (Note: should be shared with A/P and HR-Payroll)
Internal factoring is not a common process and not supported by standard SAP, hence the current solution requires nemerous complex custom developements. To "to-be" design will aim to streamline and simplify, hwever it is epected that some level of custom developments will still be required.
Risk
Cash movements related to payments and receipts is a higher risk area of any ERP implementation. The internal factoring complexity increases the risk.
Risk is a major factor in the recommendation and decision of this KDD.
Assumptions
IHB and internal factoring will continue in S4HANA.
Entities not operating within the IHB will go-live with Bank Communication Managament (BCM) in line with Overall project release\s.
Constraints
Nil
Impacts
Depending on the approach, interfaces from S4HANA to PI1 require consideration. If they are required, the existing interfaces from PF1 \ WP1 will need to be replicated for S4HANA.
The new Consolidations tool will go-live in the last release. This requires considerations for the Consolidation of the entities and processes within PI1.
Business Rules
Participation in the IHB will continue to be mandatory unless not legally supported.
Options considered
Early deployment (prior to the main S4HANA releases) of IHB was considered, however due to the impact of extending the overall ERP project timeline, and earlier transfer of master data, this option was not review in this KDD.
Option A: Defer the deployment of IHB for all GBUs\Entities until after the second group go-live.
Lowest risk option, for IHB is a high risk \ high complexity process by allowing for a fall back \ contigency for the IHB payments and receipts
Allows time to integrated process to stabalise
Allows the poption of production simulations
Interfaces need to be built between the S4HANA and PI1, although these will largely be relications of existing interfaces.
Option B: Deploy IHB for live GBUs/entities in-line with the groups of the phased deploeyment (Two IHBs).
This option entails deploying the IHB in line with the groups in the release plan. One IHB in PI1 for entites still on ECC, and a second IHB for GBUs\entities that have S4HANA for transitioned to S4HANA.
The main drawbacks with this option;
- Running two IHB can increase complexity
- Additional business resources will be required
Option C: Deploy IHB for live GBUs/entities in the first group of the phased deployment.
This option entails IHB being deployed for all entities in the first group of the release plan.
The main drawback with this option;
- Highest risk option
Option D: Deploy IHB for all GBUs/entities along with the second Group of the phased deployment.
This option entails IHB being deployed for all entities in the second group of the release plan.
This was seen at the best alternative, However the recommendation Option A is preferred due to additioanal de-risking.
Evaluation
Option A | Option B | Option C | Option D | Option A | Option B | Option C | Option D | |
|---|---|---|---|---|---|---|---|---|
De-Risk Strong Contigency \ fallback option |
|
|
|
| High | Medium | Low | Medium |
De-risk Stabilisation on integrated process (Sales\Accounts Receivable, Payments\Accounts Payables) |
| High | Low | Low | Medium | |||
De-risk Ability to run Productions Simulations | High | Low | Low | High | ||||
Less Complexity - Less Interfaces |
|
|
|
| Low | High | Medium | Medium |
Less Complexity - One IHB Operating is less complex than two IHB in operation |
|
|
|
| High | Low | High | High |
| Additional Resource Cost |
| Low | High | High | High | |||
| Business resource impact |
| High | Low | High | High | |||
| Ease of Consolidation |
Stardard process to load into Cosnsol are expected to be utilised |
Stardard process to load into Cosnsol are expected to be utilised | Medium | Medium | High | Medium | ||
| Lower Cut-over impact (less payments outages). | High | Low | High | High |
See also
Change log
Workflow history
| Title | Last Updated By | Updated | Status | |
|---|---|---|---|---|
| There are no pages at the moment. | ||||