The purpose of this document is to define the conversion approach to create Portfolio Initiatives in S/4 HANA.

This is a completely new object for Syensqo.

Portfolio Initiatives represents a Programme in EPPM. A Portfolio Initiative is group of related projects (Portfolio Items) potentially belonging to different Portfolio Buckets for reporting purposes.


Initiative Decision Point represents the stage gates for a EPPM Programme.   Although the decision point will be automatically created on creation of the Initiatives no action is required for the Initiative decision points from a data conversion perspective.



Conversion Scope

The scope of this document covers the approach for converting active Portfolio Initiatives from Legacy Source Systems into S/4HANA following the Portfolio Initiatives Master Data Design Standard.

This is a completely new object for Syensqo with the data being provided in a clean status with no requirement for exclusion of any records.


No action is required for the Initiative decision points from a data migration perspective.



The expected volume of data is ????


List of source systems and approximate number of records
SourceScope

Source Approx No. of Records

Target SystemTarget Approx

No. of Records

DCT

All Records

?

S/4HANA

?
















Additional Information

Multi-language Requirement

Initiative  names and texts will be maintained in a single language (however they are entered); translations will not be possible.

Document Management

Not Applicable

Legal Requirement

Not Applicable

Special Requirements

Not Applicable





Target Design

The technical design of the target for this conversion approach.

TableFieldData ElementField DescriptionData TypeLengthRequirement
INM_INITIATIVEEXTERNAL_IDINM_TV_EXTIDInitiative IDCHAR24Mandatory
INM_INITIATIVESTATSTATSystem statusCHAR5Mandatory
INM_INITIATIVEPORTFOLIO_ID/RPM/TV_EXTIDPortfolio IDCHAR24Mandatory
INM_INITIATIVEBUCKET_ID/RPM/TV_EXTIDParent Bucket IDCHAR24Mandatory
INM_INITIATIVEITEM_TYPE/RPM/TV_ITEM_IDInitiative TypeCHAR24Mandatory
INM_INITIATIVENAMECGPL_TEXT1Initiative NameCHAR40Mandatory
INM_INITIATIVECURRENCYRPM_TV_CURRENCYCurrency keyCUKY5Mandatory
INM_INITIATIVEPLANNED_STARTRPM_TV_PLAN_STARTPlanned StartDATS8Optional
INM_INITIATIVEPLANNED_FINISHRPM_TV_PLAN_FINISHPlanned FinishDATS8Optional
INM_INITIATIVECAP_PERIODTYPE/RPM/TV_CAP_PERIOD_TYPECapacity Period BreakdownNUMC2Mandatory
INM_INITIATIVEUNITRPM_TV_UNITUnitCHAR3Mandatory
INM_INITIATIVEPERIODTYPE/RPM/TV_PERIOD_TYPEFinancial Period BreakdownNUMC2Mandatory
INM_INITIATIVEZX001HROBJIDProgram ManagerNUMC8Mandatory
INM_INITIATIVEZX002STEXTProgram Manager Position NameSTEXT40Mandatory
INM_INITIATIVEZX003SOBIDProgram Manager IDCHAR45Mandatory
INM_INITIATIVEZX004STEXTProgram Manager NameSTEXT40Mandatory
INM_INITIATIVE

LTEXT

STXL-CLUSTDInitiative DescriptionCLUSTD
Optional


Data Cleansing

Not applicable, as data object Project Bucket Hierarchy does not exist in legacy system and will be collected specifically for data migration.


IDCriticalityError Message/Report DescriptionRuleOutputSource System


























Conversion Process

The high-level process is represented by the diagram below:


Data Privacy and Sensitivity

Not Applicable.



Extraction

Extract data from a source into . There are 2 possibilities:

  1. The data exists. connects to the source and loads the data into . There are 3 methods:
    1. Perform full data extraction from relevant tables in the source system(s).
    2. Perform extraction through the application layer.
    3. Only if ; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
  2. The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in . This is to be conducted using DCT (Data Collection Template) in

The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads

Extraction Run Sheet

Req #Requirement DescriptionTeam Responsible













Selection Screen

Selection Ref ScreenParameter NameSelection TypeRequirementValue to be entered/set





















Data Collection Template (DCT)

Target Ready Data Collection Template will be created for data with exception of some fields which require transformation as mentioned in the transformation rule.

DCT Rules

Field NameField DescriptionRule
EXTERNAL_IDInitiative IDUnique Identifier for the Initiative, system generated number. (IN-XXXXXX)
STATSystem statusRepresent the system status of an initiative.  Default Status is set upon creation of PPM Initiative. It can be modified by the Program Manager at any point during the Initiative's lifecycle.
PORTFOLIO_IDPortfolio IDLocked and Defaulted "Syensqo"
BUCKET_IDParent Bucket IDUnique Identifier for the initiative's parent Bucket. In SyWay it is the ID of the L3 bucket where item is assigned
NAMEInitiative NameName of the Initiative.
PLANNED_STARTPlanned StartOptional Format (YYYYMMDD)
PLANNED_FINISHPlanned FinishOptional Format (YYYYMMDD)
ZX001Program ManagerThis field represent Position of the Program Manager and is mandatory for all Initiatives to determine the responsibility
LTEXTInitiative DescriptionConditional for initiatives where additional program information is required

Extraction Dependencies

Item #Step DescriptionTeam Responsible













Transformation

The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow to make the data Target ready:

  1. Perform value mapping and data transformation rules.
    1. Legacy values are mapped to the to-be values (this could include a default value)
    2. Values are transformed according to the rules defined in
  2. Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation

Transformation Run Sheet

Item #Step DescriptionTeam Responsible

1

Obtain DCT Sign-off from Business

SyWay I2M Data Team

2

Load DCT using transformation rules

SyWay I2M Data Team

3

Review and Validate Error and Preload Reports

SyWay I2M Data Team

4

Generate Load Files

SyWay I2M Data Team


Transformation Rules

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic
1DCT
EXTERNAL_IDInitiative IDS/4 HanaINM_INITIATIVEEXTERNAL_IDInitiative IDCopy from source to target system
2DCT
STATSystem statusS/4 HanaINM_INITIATIVESTATSystem statusCopy from source to target system
3DCT
PORTFOLIO_IDPortfolio IDS/4 HanaINM_INITIATIVEPORTFOLIO_IDPortfolio IDCopy from source to target system
4DCT
BUCKET IDParent Bucket IDS/4 HanaINM_INITIATIVEBUCKET_IDParent Bucket IDCopy from source to target system
5DCT


S/4 HanaINM_INITIATIVEITEM_TYPEInitiative TypeDefault "Z001"
6DCT
NAMEInitiative NameS/4 HanaINM_INITIATIVENAMEInitiative NameCopy from source to target system
7DCT


S/4 HanaINM_INITIATIVECURRENCYCurrency keyDefault "EUR"
8DCT
PLANNED_STARTPlanned StartS/4 HanaINM_INITIATIVEPLANNED_STARTPlanned StartCopy from source to target system
9DCT
PLANNED_FINISHPlanned FinishS/4 HanaINM_INITIATIVEPLANNED_FINISHPlanned FinishCopy from source to target system
10



S/4 HanaINM_INITIATIVECAP_PERIODTYPECapacity Period BreakdownDefault to "12"(Annually)
11



S/4 HanaINM_INITIATIVEUNITUnitDefault to "TAG"(Day)
12



S/4 HanaINM_INITIATIVEPERIODTYPEFinancial Period BreakdownDefault to "12"(Annually)
13DCT
ZX001Program ManagerS/4 HanaINM_INITIATIVEZX001Program ManagerCopy from source to target system
14



S/4 HanaINM_INITIATIVEZX002Program Manager Position NameValue Mapping: Position Name from Position
Mapped from table field HRP1000-STEXT where HRP1000-OBJID= ZX001
15



S/4 HanaINM_INITIATIVEZX003Program Manager IDValue Mapping: Personal ID from Position
Mapped from table field HRP1001-SOBID where HRP1001-SCLAS=P, OTYPE=S & OBJID=ZX001
16



S/4 HanaINM_INITIATIVEZX004Program Manager NameValue Mapping: Personal Name from Position
Mapped from table field HRP1000-STEXT where HRP1000-OBJID=ZX003
17DCT
LTEXTInitiative DescriptionS/4 HanaINM_INITIATIVELTEXTInitiative DescriptionCopy from source to target system

List of Custom Target Reports for this object is maintained here: Conversion Specification - Custom Reports Register.

Transformation Mapping

Mapping Table NameMapping Table Description

HRP1000

Infotype 1000 DB Table
HRP1001Infotype 1001 DB Table




Transformation Dependencies

List the steps that need to occur before transformation can commence
Item #Step DescriptionTeam Responsible
1Position table HRP1000 has been maintained (HRP1000)
2Position table HRP1001 has been maintained (HRP1001)







Pre-Load Validation

Project Team

Completeness

TaskAction

Verify Record Count

SyWay I2M Data Team to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets.






Accuracy

TaskAction

Conversion Accuracy

SyWay I2M Data Team to verify that all fields below meet pass the checks:

  1. Mandatory Fields
  2. Field and Value Mapping Correctness
  3. Null Checks
  4. Text Length Checks

Review Error Reports

Review and correct the errors.  Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source (DCT) data.




Business

Completeness

TaskAction

Verify Record Count

Business Data Owner/s to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets.






Accuracy

TaskAction

Conversion Accuracy

Business Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules (and signed-off DCT data).






Load

The load process includes:

  1. Execute the automated data load into target system using load tool or product the load file if the load must be done manually
  2. Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation

Load Run Sheet

Item #Step DescriptionTeam Responsible

1

Go to RPM_DX_INITIATIVE

SyWay I2M Data Team

2

Load 3 records for < > to validate if data is loaded successfully without errors

SyWay I2M Data Team

3

Load 3 records for < > to validate if data is loaded successfully without errors

SyWay I2M Data Team

4

Proceed with full load if steps 2 and 3 are validated

SyWay I2M Data Team

5

Validate few records loaded by accessing Portfolio Initiative App

SyWay I2M Data Team

6

Generate post load report if step 5 is validated

SyWay I2M Data Team


Load Phase and Dependencies

Configuration

Item #Configuration Item
1Initiative Type (/RPM/ITEM_TYPE)




Conversion Objects

Object #Preceding Object Conversion Approach
1113Portfolio Bucket Hierarchy




Error Handling

Error TypeError DescriptionAction Taken

Invalid Data

Invalid Portfolio

Validate DCT default content

Invalid Data

Invalid Bucket ID

Validate DCT default content





Post-Load Validation

Project Team

Completeness

TaskAction

Verify Count

SyWay I2M Data Team to verify the record count created in target S/4 HANA by accessing post load reports or standard reports from S/4 HANA.

Verify Logs

Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.).




Accuracy

TaskAction
Conversion AccuracyVerify that the Portfolio Initiatives in target S/4 HANA were loaded correctly via Initiative Dashboard App display and table V_INM_INIT_DB in S/4 HANA





Business

Completeness

TaskAction

Verify Count

Extract Initiative details from Initiative dashboard App in S/4 HANA






Accuracy

TaskAction
Verify AccuracyExtract Initiative details from Initiative dashboard App in S/4 HANA





Key Assumptions

  • Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
  • Portfolio Initiatives is in scope based on data design and any exception requested by business.


See also

Change log

Version Published Changed By Comment
CURRENT (v. 6) Apr 21, 2026 13:11 NADAR-ext, Parvati
v. 21 Apr 01, 2026 18:56 NADAR-ext, Parvati
v. 20 Mar 24, 2026 11:28 NADAR-ext, Parvati
v. 19 Mar 23, 2026 09:46 NADAR-ext, Parvati
v. 18 Mar 09, 2026 20:01 NADAR-ext, Parvati
v. 17 Feb 19, 2026 09:37 NADAR-ext, Parvati
v. 16 Nov 12, 2025 14:49 NADAR-ext, Parvati
v. 15 Nov 10, 2025 16:31 NADAR-ext, Parvati
v. 14 Oct 06, 2025 16:01 NADAR-ext, Parvati
v. 13 Oct 03, 2025 16:28 NADAR-ext, Parvati

Go to Page History

  • No labels