| Status | Approved |
|---|---|
| Owner | |
| Stakeholders |
Purpose
The purpose of this document is to define the conversion approach to create Project Budget in S/4 HANA.
Conversion Scope
The scope of this document covers the approach for converting Project Budgets from Legacy Source Systems into Project and Item Budgets in S/4HANA.
For items created with legacy project id's the budget for the item will be the annual budget of the level 1 WBS element from the legacy system with some enrichment requirements, there is also requirement to capture budget for items which is not available in source system.
The data from legacy system includes:
- Level 1 WBS element budgets for S/4 PPM Items with Legacy Project ID as created in CNV-1022 Portfolio Item
The data from legacy system excludes:
Additionally, there will be Items included in the DCT which does not have Budget in the legacy system
- Projects with legacy ID
- IT Projects
- R&I Projects
- Projects with no legacy ID
- Direct Asset purchases for which an Item is created for GBU/Company Code/Plant combination
- Capital Spare for which an item is created for GBU/Company Code/Plant combination
- Capital Lease for which an item is created for GBU/Company Code/Plant combination
- Cluster Item
- Budget Provision Item
List of source systems and approximate number of records
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
| PF2 | Annual WBS Budget values for projects migrated through CNV-1022 PPM Items | 5000 | S/4 Hana | 4000 |
| WP2 | Annual WBS Budget values for projects migrated through CNV-1022 PPM Items | 9000 | S/4 Hana | 6000 |
| DCT | Annual WBS Budget values for projects which have no budget in Source (e.g. IT and R&I) | |||
After loading the budget to the PPM Item the budget is transferred to the level 1 WBS element where the WBS elements have been created.
Selection Logic
Get Legacy Project Internal number ( from table PROJ using the Legacy Project ID from the S/4 PPM item
Get Level 1 WBS Object Number ( ) from table PRPS legacy using the Legacy Project internal number and Stufe="1"
Get Budget Value ( ) and Year ( ) from table BPJA using Level 1 WBS Object Number, Value Type ="41" and Budget Type =
Additional Information
Multi-language Requirement
Not Applicable
Document Management
Not Applicable
Legal Requirement
Not Applicable
Special Requirements
Not Applicable
Target Design
The technical design of the target for this conversion approach.
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| /RPM/FIN_PLAN | EXTERNAL_ID | /RPM/TV_EXTID | Item ID | CHAR | 24 | Mandatory |
| /RPM/FIN_PLAN | FIN_VIEW_ID | /RPM/TV_FIN_VIEW | Financial View Type | NUM | 2 | Mandatory |
| /RPM/FIN_PLAN | FIN_VIEW_DESC | /RPM/TV_FIN_VIEW_DESC | Financial View Name | CHAR | 40 | Mandatory |
| /RPM/FIN_PLAN | CATEGORY_ID | /RPM/TV_FIN_CATG | Financial Category | CHAR | 15 | Mandatory |
| /RPM/FIN_PLAN | CATEGORY_TEXT | /RPM/TV_FIN_CATG_T | Financial Category text | CHAR | 80 | Mandatory |
| /RPM/FIN_PLAN | GROUP_ID | /RPM/TV_FIN_GRP | Financial Group | CHAR | 15 | Mandatory |
| /RPM/FIN_PLAN | GROUP_TEXT | /RPM/TV_FIN_GRP_T | Financial Group text | CHAR | 80 | Mandatory |
| /RPM/FIN_PLAN | PERIOD | /RPM/TV_START_DATE | Start Date | DATS | 8 | Mandatory |
| /RPM/FIN_PLAN | AMOUNT | /RPM/TV_CURR_AMOUNT | Financial Amount | NUM | 26 | Mandatory |
| /RPM/FIN_PLAN | CURRENCY | /RPM/TV_CURRENCY | Currency | CHAR | 5 | Mandatory |
| /RPM/FIN_PLAN | PERIOD_TYPE | /RPM/TV_PER_CONVFACTOR | Period Conversion Factor | NUM | 2 | Mandatory |
| BPJA | OBJNR | BP_OBJEKT | Object number | CHAR | 22 | Mandatory |
| BPJA | WRTTP | CO_WRTTP | Value Type | CHAR | 2 | Mandatory |
| BPJA | GJAHR | GJAHR | Fiscal Year | NUMC | 4 | Mandatory |
| BPJA | VORGA | BP_VORGANG | Budget Type | CHAR | 4 | Mandatory |
| BPJA | TWAER | TWAER | Transaction Currency | CUKY | 5 | Mandatory |
| BPJA | WTJHR | BP_WJT | Annual value | CURR | 21 | Mandatory |
Data Cleansing
Cleansing is done on the master data objects to which the budgets relate, no specific budget cleansing is required.
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|
Conversion Process
The high-level process is represented by the diagram below:
Data Privacy and Sensitivity
Is there privacy and sensitivity concerns for project budgets?
Extraction
Extract data from a source into Syniti Migrate. There are 2 possibilities:
- The data exists. Syniti Migrate connects to the source and loads the data into Syniti Migrate. There are 3 methods:
- Perform full data extraction from relevant tables in the source system(s).
- Perform extraction through the application layer.
- Only if Syniti Migrate; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
- The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
Extraction Run Sheet
| Req # | Requirement Description | Team Responsible |
|---|---|---|
| 1 | Extract data from source system | SyWay Data Team |
| 1 | Ensure DCT is collected | Data Team |
| 2 | Perform preliminary completeness check, data quality check. | Data Team |
| 3 | Raise issues as defects if Req # 1 to 2 are not met | Data Team |
| 4 | Repeat Req # 1 to 3 if required | Data Team |
Selection Screen
| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
| Not Applicable |
Data Collection Template (DCT)
Target Ready Data Collection Template will be created for Project Budget data with exception of some fields which require transformation as mentioned in the transformation rule.Project Budget DCT Rules
Item Level
| Field Name | Field Description | Rule |
|---|---|---|
| EXTERNAL_ID | PPM Item ID | This is a dropdown field of PPM Items The values are restricted to the PPM items created in CNV-1022, for selection both the item number and Name is to be displayed. |
| SG_CATEGORY | Suggested Financial Category | |
| CATEGORY_TEXT | Financial Category text | This is a dropdown field that differentiates between the Capital and Operating Financial Categories. |
| YEAR | Fiscal Year | This is the fiscal year to which the budget is assigned |
| AMOUNT | Financial Amount | The Approved funding value for the year |
WBS Level
| Field Name | Field Description | Rule |
|---|---|---|
| PSPID | Project Definition | This is a dropdown field of Project Definitions The values are restricted to the Project Definitions created in CNV-1022, for selection both the item number and Name is to be displayed. |
| POSID | WBS Element | This is a dropdown field of Phase level WBS Elements of the project selected PRPS with STUFE = 2 and PSPHI = PSPID |
| YEAR | Fiscal Year | This is the fiscal year to which the budget is assigned |
| WTJHR | Amount | The budget assigned to the phase |
Extraction Dependencies
| Item # | Step Description | Team Responsible |
|---|---|---|
Transformation
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:
- Perform value mapping and data transformation rules.
- Legacy values are mapped to the to-be values (this could include a default value)
- Values are transformed according to the rules defined in Syniti Migrate
- Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation
Transformation Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1 | Execute and Load and perform Transformation | Data Team |
| 2 | Monitor the transformation progress and ensure performance and completion is within allowed timeframe | Data team |
| 3 | Review and Validate Error and Preload Reports | Data Team |
| 4 | Generate data load count. | Data team |
| 5 | Generate Load Files | Data Team |
| 6 | Log errors as defects, if any and address resolutions. Close defects. | Data team |
| 7 | Re-transform and re-validate the Pre-load reports if necessary. | Data team |
| 8 | Validate the transformed file as part of pre-load validation, raise data defects or provide the pre-load sign-off. | Business |
| 9 | Analyze and resolve any pre-load defects logged by business. | Data team |
| 10 | Repeat steps 7 to 10 if necessary | Data team |
| 11 | Proceed to pre-load validations | Data team |
Transformation Rules
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| WP2/PF2 | PROJ | PSPID | Project ID | S/4 Hana | /RPM/ITEM_D | EXTERNAL_ID | Item ID | Select the ID field from /RPM/ITEM_D where legacy project ID = PSPID | |
| S/4 Hana | /RPM/FIN_PLAN | FIN_VIEW_ID | Financial View Type | Default to Approved Funding | |||||
| S/4 Hana | FIN_VIEW_DESC | Financial View Name | If required read from | ||||||
| S/4 Hana | /RPM/FIN_CAT | CATEGORY_ID | Financial Category | Select from CATEGORY_T using CATEGORY_TEXT | |||||
| S/4 Hana | /RPM/FIN_GROUP | GROUP_ID | Financial Group | Default | |||||
| S/4 Hana | GROUP_TEXT | Financial Group text | Select from /RPM/FIN_GROUPST using CATEGORY_ID and GROUP_ID | ||||||
| WP2/PF2 | BPJA | GJAHR | S/4 Hana | /RPM/FIN_PLAN | PERIOD | Start Date | Convert year into yyyymmdd by adding 0101 | ||
| WP2/PF2 | BPJA | BP_WJT | S/4 Hana | /RPM/FIN_PLAN | AMOUNT | Financial Amount | Copy from Source | ||
| WP2/PF2 | BPJA | TWAER | S/4 Hana | /RPM/FIN_PLAN | CURRENCY | Currency | Copy from Source | ||
| S/4 Hana | /RPM/FIN_PLAN | PERIOD_TYPE | Period Conversion Factor | Default value "12" | |||||
| DCT | Item | EXTERNAL_ID | Item ID | Manually copy from Non ECC source | |||||
| DCT | Item | CATEGORY_TEXT | Financial Category text | CATEGORY_TEXT | Manually copy from Non ECC source, this will always be filled by users. | ||||
| DCT | Item | YEAR | Fiscal Year | S/4 Hana | PERIOD | Convert year into yyyymmdd by adding 0101 to | |||
| DCT | Item | AMOUNT | Financial Amount | S/4 Hana | BPGA | AMOUNT | Manually copy from Non ECC source | ||
| DCT | WBS | PSPID | WBS Element | S/4 Hana | BPGA | PSPID | |||
| DCT | WBS | YEAR | Fiscal Year | S/4 Hana | BPGA | YEAR | |||
| DCT | WBS | WTJHR | Amount | S/4 Hana | BPGA | WTJHR |
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| DCT | WBS | PSPID | WBS Element | S/4 Hana | BPGA | PSPID | |||
| DCT | WBS | YEAR | Fiscal Year | S/4 Hana | BPGA | YEAR | |||
| DCT | WBS | WTJHR | Amount | S/4 Hana | BPGA | WTJHR | |||
Transformation Mapping
| Mapping Table Name | Mapping Table Description |
|---|---|
Transformation Dependencies
List the steps that need to occur before transformation can commence| Item # | Step Description | Team Responsible |
|---|---|---|
| Ensure all the fields that require value mapping, as stipulated. Mapping tables, have the correct values mapped and imported into tool. | Syway Data Team |
Pre-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
| Verify Record Count | SyWay I2M Data Team to verify that the total number of relevant records in the Preload and Load Sheets. |
Accuracy
| Task | Action |
|---|---|
| Conversion Accuracy | SyWay I2M Data Team to verify that all fields below meet pass the checks:
|
| Review Error Reports | Review and correct the errors. Achieve a zero-error record count as much as possible. |
Business
Completeness
| Task | Action |
|---|---|
| Verify Record Count | Business Data Owner/s to verify that the total number of records in the Preload and Load Sheets. |
Accuracy
| Task | Action |
|---|---|
| Conversion Accuracy | Business Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules. |
Load
The load process includes:
- Execute the automated data load into target system using load tool or product the load file if the load must be done manually
- Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation
Load Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1 | Propose use of standard load program RPM_DX_FINPLAN | SyWay I2M Data Team |
| 2 | Load 3 records for < > to validate if data is loaded successfully without errors | SyWay I2M Data Team |
| 3 | Proceed with full load if steps 2 and 3 are validated | SyWay I2M Data Team |
| 4 | Validate few records loaded by accessing Portfolio Initiative App | SyWay I2M Data Team |
| 5 | Generate post load report if step 5 is validated | SyWay I2M Data Team |
| 6 | Execute program for transfer from PPM to PS | SyWay I2M Data Team |
| 7 | Validate few records loaded by accessing Portfolio Initiative App | SyWay I2M Data Team |
| 8 | Generate post load report if step 7 is validated | SyWay I2M Data Team |
Load Phase and Dependencies
Configuration
| Item # | Configuration Item |
|---|---|
| 1 | Financial Category |
| 2 | Financial Group |
| 3 | Financial View |
| 4 | Period Conversion Factor |
| 5 | PS Budget Profile |
Conversion Objects
| Object # | Preceding Object Conversion Approach |
|---|---|
| 1022 | Portfolio Item |
Error Handling
| Error Type | Error Description | Action Taken |
|---|---|---|
| Invalid Data | Item number does not exist | Validate Transformation rules and DCT values |
| Invalid Data | Financial Category does not exist | Validate transformation rules |
| Invalid Data | Financial Group does not exist | Validate transformation rules |
| Invalid Data | Financial View does not exist | Validate transformation rules |
Post-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
Verify Count Item | SyWay I2M Data Team to verify the record count created in target S/4 HANA by accessing post load reports or standard reports from S/4 HANA. |
Verify Logs Item | Check if there is data that failed to load for PPM Item and perform the necessary actions (e.g. register as post load issue or attempt to the record again, etc.). |
Verify Count WBS | SyWay I2M Data Team to verify the record count created in target S/4 HANA by accessing post load reports or standard reports from S/4 HANA. |
Verify Logs WBS | Check if there is data that failed to load for PPM Item and perform the necessary actions (e.g. register as post load issue or attempt to the record again, etc.).
|
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Verify that the approved funding were loaded to S/4 HANA correctly via table /rpm/fin_plan |
Conversion Accuracy | Verify that the budget were loaded to S/4 HANA correctly via table BPGE |
Business
Completeness
| Task | Action |
|---|---|
| Verify Item Budget | Extract approved funding from PPM ??? |
| Verify Level 1 WBS element Budget | Extract budget from PS report?? |
Accuracy
| Task | Action |
|---|---|
| Verify Accuracy | Verify approved funding for PPM objects align with expected values |
| Verify Accuracy | Verify budget for level 1 WBS elements align with related PPM items. |
Key Assumptions
- Project Budget is in scope based on data design and any exception requested by business.