Purpose

The purpose of this document is to define the conversion approach to create Project Budget in S/4 HANA.

In the Syway Project budget is used to assign active availability control on Capital Projects while providing a binding financial plan for budget managed Operating Projects.


Conversion Scope

The scope of this document covers the approach for converting Project Budgets from Legacy Source Systems into Project in S/4HANA.

A report is executed to transfer budget from the PPM item, migrated as per CNV-9035 Portfolio Item - Financial Plan,  to Level 1 WBS elements while a DCT provides the distribution of budget to Phase Level WBS elements should this be required.


Relevancy

The data from legacy system includes:

  1. PPM Items with Level 1 WBS elements in S/4 Hana

The data from legacy system excludes:

  

List of source systems and approximate number of records
SourceScope

Source Approx No. of Records

Target SystemTarget Approx

No. of Records

S/4PPM items with level 1 WBS elements10000S/4 Hana10000
DCTBudget for level 2 WBS elementsTBDS/4 HanaTBD







Selection Logic

RPM_OBJECT

Additional Information

Multi-language Requirement

Not Applicable

Document Management

Not Applicable

Legal Requirement

Not Applicable

Special Requirements

Not Applicable




Target Design

The technical design of the target for this conversion approach.

TableFieldData ElementField DescriptionData TypeLengthRequirement
BPGEOBJNRBP_OBJEKTObject numberCHAR22Mandatory
BPGEWRTTPCO_WRTTPValue TypeCHAR2Mandatory
BPGEGJAHRGJAHRFiscal YearNUMC4Mandatory
BPGEVORGABP_VORGANGBudget TypeCHAR4Mandatory
BPGETWAERTWAERTransaction CurrencyCUKY5Mandatory
BPGEWTJHRBP_WJTAnnual valueCURR21Mandatory


Data Cleansing

Cleansing is done on the master data objects to which the budgets relate, no specific budget cleansing is required.

IDCriticalityError Message/Report DescriptionRuleOutputSource System



Conversion Process

The high-level process is represented by the diagram below:


Data Privacy and Sensitivity

N/A


Extraction

Extract data from a source into Syniti Migrate. There are 2 possibilities:

  1. The data exists. Syniti Migrate connects to the source and loads the data into Syniti Migrate. There are 3 methods:
    1. Perform full data extraction from relevant tables in the source system(s).
    2. Perform extraction through the application layer.
    3. Only if Syniti Migrate; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
  2. The data does not exist (or cannot be converted from its current state).  The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate

The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads

Extraction Run Sheet

Req #Requirement DescriptionTeam Responsible
1Extract data from source systemSyWay Data Team
1Ensure DCT is collectedData Team
2Perform preliminary completeness check, data quality check.Data Team
3

Raise issues as defects if Req # 1 to 2 are not met

Data Team
4

Repeat Req # 1 to 3 if required

Data Team


Selection Screen

Selection Ref ScreenParameter NameSelection TypeRequirementValue to be entered/set
Not Applicable




Data Collection Template (DCT)

Target Ready Data Collection Template will be created for Project Budget data with exception of some fields which require transformation as mentioned in the transformation rule.

Project Budget DCT Rules


WBS Level

Field NameField DescriptionRule
PARENTLevel 1 WBS Element

The Level 1 WBS elements budget is assigned from the PPM item.

The values are restricted to the Level 1 WBS created in CNV-1022, for selection both the item number and Name is to be displayed.

This is a required field for capturing but not relevant for Preload validations.

PARENT_BUDGETLevel 1 Budget

The field displays the budget assigned to the Parent WBS element.

This is a calculated field assisting user with understanding the value available for assignment to the lower levels and is used in the preload validation of the Amount field.

POSIDWBS Element

This is a dropdown field of Phase level WBS Elements of the project selected.

The values are restricted to the Level 2 WBS elements created in CNV-1022 and further restricted by the PARENT selected.   For selection both the item number and Name is to be displayed.

This is a required field.

WTJHRAmount

The budget assigned to the phase

Preload validation the Sum of Amount fields for all POSID's linked to the same PARENT may not be more than the PARENT_BUDGET

Extraction Dependencies

Item #Step DescriptionTeam Responsible

Execute report to transfer budget from PPM to PSSyway I2M Data Team

Run Extraction Report on S/4







Transformation

The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:

  1. Perform value mapping and data transformation rules.
    1. Legacy values are mapped to the to-be values (this could include a default value)
    2. Values are transformed according to the rules defined in Syniti Migrate
  2. Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation

Transformation Run Sheet

Item #Step DescriptionTeam Responsible
1Execute Extract and perform Transformation Data Team
2Monitor the transformation progress and ensure performance and completion is within allowed timeframeData team
3Review and Validate Error and Preload ReportsData Team
4Generate data load count.Data team
5Generate Load FilesData Team
6Log errors as defects, if any and address resolutions. Close defects.Data team
7Re-transform and re-validate the Pre-load reports if necessary.Data team
8Validate the transformed file as part of pre-load validation, raise data defects or provide the pre-load sign-off.Business
9Analyze and resolve any pre-load defects logged by business.Data team
10Repeat steps 7 to 10 if necessaryData team
11Proceed to pre-load validationsData team


Transformation Rules

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic


List of Custom Target Reports for this object is maintained here: Conversion Specification - Custom Reports Register.

The Standard template for the upload of Item financials that can be used for the upload of project budget, this includes ability to upload of custom fields, into S/4 Hana:  Item Budget Load File.xlsx - Google Sheets


Transfer Item Budget to the Level 1 WBS element via a report which is run /RPM/CO_DOWNLOAD, execution of report is restricted By Portfolio ID and  Lowest level bucket ID.

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic

DCTWBSPSPIDWBS ElementS/4 HanaBPGEPSPID
 Manually copy from Non ECC source

DCTWBSWTJHRAmountS/4 HanaBPGEWTJHR
 Manually copy from Non ECC source


Once the above report has been execute the distribution of the budget to Level 2 WBS elements can be performed. 


Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic

DCTWBSPSPIDWBS ElementS/4 HanaBPGEPSPID
 Manually copy from Non ECC source

DCTWBSWTJHRAmountS/4 HanaBPGEWTJHR
 Manually copy from Non ECC source









 

Transformation Mapping

Mapping Table NameMapping Table Description


Transformation Dependencies

List the steps that need to occur before transformation can commence
Item #Step DescriptionTeam Responsible

Ensure all the fields that require value mapping, as stipulated. Mapping tables, have the correct values mapped and imported into tool.Syway Data Team


Pre-Load Validation

Project Team

Completeness

TaskAction
Verify Record CountSyWay I2M Data Team to verify that the total number of relevant records in the Preload and Load Sheets.

Accuracy

TaskAction
Conversion Accuracy

SyWay I2M Data Team to verify that all fields below meet pass the checks:

  1. Mandatory Fields
  2. Field and Value Mapping Correctness
  3. Null Checks
  4. Text Length Checks
Review Error ReportsReview and correct the errors.  Achieve a zero-error record count as much as possible.

Business

Completeness

TaskAction
Verify Record CountBusiness Data Owner/s to verify that the total number of records in the Preload and Load Sheets.

Accuracy

TaskAction
Conversion AccuracyBusiness Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules.


Load

The load process includes:

  1. Execute the automated data load into target system using load tool or product the load file if the load must be done manually
  2. Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation

Load Run Sheet

Item #Step DescriptionTeam Responsible
1

Execute standard program for transfer from PPM to PS

SyWay I2M Data Team
2

Validate few records loaded by accessing WBS Budget App

SyWay I2M Data Team
3

Generate post load report if step 2 is validated

SyWay I2M Data Team
4

Load WBS level 2 budget using custom or standard upload

SyWay I2M Data Team
5

Validate few records loaded by accessing WBS Budget App

SyWay I2M Data Team
6

Generate post load report if step 5 is validated

SyWay I2M Data Team


Load Phase and Dependencies

Configuration

Item #Configuration Item
1PS Budget Profile

Conversion Objects

Object #Preceding Object Conversion Approach
1022Portfolio Item
1026WBS Element CAPEX/OPEX/STATISTICAL

Error Handling

Error TypeError DescriptionAction Taken
Invalid DataWBS element does not existCorrect DCT values
Invalid DataBudget Assigned to Lower level is greater than the Parent BudgetInvestigate the reason for error and update DCT values accordingly


Post-Load Validation

Project Team

Completeness

TaskAction

Verify Count WBS

SyWay I2M Data Team to verify the record count created in target S/4 HANA by accessing post load reports or standard reports from S/4 HANA.

Verify Logs WBS

Check if there is data that failed to load for PPM Item and perform the necessary actions (e.g. register as post load issue or attempt to the record again, etc.).

 


Accuracy

TaskAction

Conversion Accuracy

Verify that the budget were loaded to S/4 HANA correctly via table BPGE


Business

Completeness

TaskAction
Verify WBS element BudgetExtract budget from PS report.

Accuracy

TaskAction
Verify AccuracyVerify budget for level 1 WBS elements align with related PPM items.
Verify AccuracyVerify distributed budget for level 2 WBS elements align with expected values


Key Assumptions

  • Project Budget is in scope based on data design and any exception requested by business.


See also

Change log

Version Published Changed By Comment
CURRENT (v. 12) Dec 08, 2025 14:08 KOHN-ext, Jacob
v. 18 Dec 08, 2025 14:05 KOHN-ext, Jacob
v. 17 Dec 08, 2025 14:02 KOHN-ext, Jacob
v. 16 Nov 20, 2025 09:40 KOHN-ext, Jacob
v. 15 Nov 19, 2025 14:18 KOHN-ext, Jacob
v. 14 Nov 19, 2025 14:13 KOHN-ext, Jacob
v. 13 Nov 19, 2025 13:08 KOHN-ext, Jacob
v. 12 Nov 19, 2025 08:01 KOHN-ext, Jacob
v. 11 Nov 17, 2025 16:00 KOHN-ext, Jacob
v. 10 Nov 17, 2025 13:59 KOHN-ext, Jacob

Go to Page History

  • No labels