Percentage of obsolete combinations
| Indicator | Percentage of obsolete combinaisons |
|---|---|
| Stream | Indus - F&P |
| Process / Sub-process | Forecasting |
| Target | 5% |
| Expected Evolution | ↓ |
| Comparaison between entities | Coherent |
Definition
Percentage of couples Material x Customer Ship-to without Demand History in the last 12 months. Where the demande History is the history of the sales orders' quantities at the issue date calculated from the last delivery date requested by the customer.
Good practice
The good practice is to clean out regulary the APO database, trying to have less than 5 % of obsolete combinations. A high level of obsolete combination will introduce errors on the statistical forecast calculation and will difficult the navigation in the Interactive Planning and Reports; eventually it could have consecuences on the system response time.
Calculation
Number of obsolete Material x Cust Ship To Combinations / Total nb of Material x Cust Ship To combinations * 100
Analysis axes
Enterprise / Geographique Zone / Plant
Percentage of volume with sales forecasts
Indicator | Percentage of volume with sales forecasts |
|---|---|
Stream | Indus - F&P |
Process / Sub-process | Forecasting |
Target | 80 % |
Expected Evolution | ↑ |
Comparaison between entities | Coherent |
Definition
Percentage of volume of couples Material x Customer Ship-to with Sales Forecast
Good practice
In an effort to develop an efficient forecast management approach, it is interesting to segment the combinations based on their volume following the Pareto's rule. The good practice will be to forecast by the Sales Team, at least the High volumen combinations (they should represent at least 80 % of total volume.)
Calculation
Volume of Demand History of "Material x Cust Ship-To" combinations with Sales Forecast / Volume of Demand History of Total "Material x Cust Ship-To" combinations * 100
Analysis axes
Enterprise / Geographique Zone / Plant
Demand Plan Process
Indicator | Demand Plan Process |
|---|---|
Stream | Indus - F&P |
Process / Sub-process | Forecasting |
Target | It should be 2 - it's not a percentage |
Expected Evolution | To green (2) |
Comparaison between entities | Coherent |
Definition
Follows if the standard demand plan process is done every month, by monotoring the 2 main steps :
- Consolidation of the Pre-SOIP Demand Plan
- Release of the Post-SOIP Committed Plan
Demand Process :
Good practice
As SOIP is a monthly process, the Pre-SOIP demand plan consolidation should be triggered at least once a month and to enable the planning process to be performed, the Post SOIP committed plan should be published at least once a month
Calculation
- 0 -> if none of both steps were not triggered (red)
- 1 -> if only one step was triggerd (yellow)
- 2 -> if both steps were triggered (green)
Analysis axes
Enterprise / Geographique Zone / Demand Planer perimeter
The best way to get IT support is to use the new
Service One Platform.
